Greenspoint at Emaar South, Dubai

Construction progress

Greenspoint at Emaar South, Dubai construction updates

Dubai South · Emaar Dubai South Dwc Llc

Under constructionLast site inspection July 21, 2026 · 4 months ago
42.9%complete

When DLD first inspected the site on Jan 22, 2025, it was 0% complete. After 6 inspections it now stands at 42.9%.

That is about 2.4% more of the building completed each month on average.

First inspection · 0%Latest · 42.9%
Construction started
January 30, 2025
Completion date registered with DLD
March 31, 2029
Site inspections
6
Units
196
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3514

Latest site photos

July 21, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. July 21, 2026

    3 months after the previous inspection

    +16.6%42.9%
  2. April 21, 2026

    5 months after the previous inspection

    +18.3%26.3%
  3. November 25, 2025

    0 days after the previous inspection

    8%
  4. November 25, 2025

    4 months after the previous inspection

    +6.6%8%
  5. July 30, 2025

    6 months after the previous inspection

    +1.4%1.4%
  6. January 22, 2025

    First inspection

    0%

Thinking about Greenspoint at Emaar South, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3514), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.