Greenspoint 2 at Emaar South, Dubai

Construction progress

Greenspoint 2 at Emaar South, Dubai construction updates

Dubai South · Emaar Dubai South Dwc Llc

Under constructionLast site inspection August 3, 2026 · 3 months ago
40.1%complete

When DLD first inspected the site on Feb 11, 2025, it was 0% complete. After 4 inspections it now stands at 40.1%.

That is about 2.3% more of the building completed each month on average.

First inspection · 0%Latest · 40.1%
Construction started
January 30, 2025
Completion date registered with DLD
March 31, 2029
Site inspections
4
Units
244
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3558

Latest site photos

August 3, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. August 3, 2026

    3 months after the previous inspection

    +19.8%40.1%
  2. April 21, 2026

    5 months after the previous inspection

    +10.7%20.3%
  3. November 27, 2025

    9 months after the previous inspection

    +9.6%9.6%
  4. February 11, 2025

    First inspection

    0%

Thinking about Greenspoint 2 at Emaar South, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3558), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.