Greenridge at Emaar South, Dubai by Emaar Properties

Construction progress

Greenridge at Emaar South, Dubai by Emaar Properties construction updates

Emaar South · Emaar Dubai South Dwc Llc

Under constructionLast site inspection June 17, 2026 · 5 months ago
35.6%complete

When DLD first inspected the site on Sep 9, 2024, it was 0% complete. After 6 inspections it now stands at 35.6%.

That is about 1.7% more of the building completed each month on average.

First inspection · 0%Latest · 35.6%
Construction started
January 30, 2025
Completion date registered with DLD
December 31, 2028
Site inspections
6
Units
520
Escrow bank
Mashreq Bank Psc
DLD project no.
3283

Latest site photos

June 17, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. June 17, 2026

    4 months after the previous inspection

    +9.2%35.6%
  2. February 9, 2026

    3 months after the previous inspection

    +20.8%26.4%
  3. October 29, 2025

    4 months after the previous inspection

    +4.6%5.6%
  4. July 1, 2025

    3 months after the previous inspection

    +0.3%1%
  5. March 20, 2025

    6 months after the previous inspection

    +0.7%0.7%
  6. September 9, 2024

    First inspection

    0%

Thinking about Greenridge at Emaar South, Dubai by Emaar Properties?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3283), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.