Golf Hills by Emaar

Construction progress

Golf Hills by Emaar construction updates

Dubai South · Emaar Dubai South Dwc Llc

Under constructionLast site inspection June 23, 2026 · 5 months ago
3.7%complete

When DLD first inspected the site on Sep 24, 2025, it was 0% complete. After 3 inspections it now stands at 3.7%.

That is about 0.4% more of the building completed each month on average.

First inspection · 0%Latest · 3.7%
Construction started
December 30, 2025
Completion date registered with DLD
September 30, 2029
Site inspections
3
Units
204
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
4117

Latest site photos

June 23, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. June 23, 2026

    3 months after the previous inspection

    +3.4%3.7%
  2. March 13, 2026

    6 months after the previous inspection

    +0.2%0.2%
  3. September 24, 2025

    First inspection

    0%

Thinking about Golf Hills by Emaar?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4117), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.