Golf Heights at Emirates Living

Construction progress

Golf Heights at Emirates Living construction updates

Emirates Living Dubai · Emaar Properties (P.J.S.C)

CompletedLast site inspection June 17, 2026 · 5 months ago
100%complete

DLD first inspected the site on Oct 6, 2022 at 0% complete, and recorded it as finished after 11 inspections, the last on Jun 17, 2026.

First inspection · 0%Latest · 100%
Construction started
March 26, 2023
Completion date registered with DLD
December 31, 2026
Site inspections
11
Units
281
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2469

Latest site photos

June 17, 2026

Progress over time

Progress over time
0%25%50%75%100%2023202420252026

Inspection history

  1. June 17, 2026

    36 days after the previous inspection

    +2.7%100%
  2. May 12, 2026

    3 months after the previous inspection

    +8.2%97.3%
  3. February 3, 2026

    4 months after the previous inspection

    +5.8%89.1%
  4. October 6, 2025

    4 months after the previous inspection

    +13.1%83.3%
  5. May 29, 2025

    5 months after the previous inspection

    +26.3%70.2%
  6. January 6, 2025

    4 months after the previous inspection

    +20.1%44%
  7. September 9, 2024

    6 months after the previous inspection

    +11.3%23.9%
  8. March 22, 2024

    6 months after the previous inspection

    +7.2%12.5%
  9. September 19, 2023

    3 months after the previous inspection

    +4.9%5.4%
  10. June 12, 2023

    8 months after the previous inspection

    +0.4%0.4%
  11. October 6, 2022

    First inspection

    0%

Thinking about Golf Heights at Emirates Living?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2469), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.