Genesis Residences at Al Barsha, Dubai

Construction progress

Genesis Residences at Al Barsha, Dubai construction updates

Al Satwa Dubai · Meraki Real Estate Development L.L.C

CompletedLast site inspection February 25, 2020 · 7 years ago
100%complete

DLD first inspected the site on Apr 2, 2018 at 20% complete, and recorded it as finished after 6 inspections, the last on Feb 25, 2020.

First inspection · 20%Latest · 100%
Construction started
September 25, 2017
Completion date registered with DLD
February 25, 2020
Site inspections
6
Units
200
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2044

Latest site photos

February 25, 2020

Progress over time

Progress over time
0%25%50%75%100%20192020

Inspection history

  1. February 25, 2020

    13 days after the previous inspection

    +0.9%100%
  2. February 12, 2020

    10 months after the previous inspection

    +19%99.1%
  3. April 17, 2019

    3 months after the previous inspection

    +15.1%80.1%
  4. January 21, 2019

    5 months after the previous inspection

    +19.8%65%
  5. September 5, 2018

    5 months after the previous inspection

    +25.3%45.3%
  6. April 2, 2018

    First inspection

    20%

Thinking about Genesis Residences at Al Barsha, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2044), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat