Gardens 2 by IMAN Developers at Arjan Dubai

Construction progress

Gardens 2 by IMAN Developers at Arjan Dubai construction updates

Arjan Dubai · Iman Developers L.L.C

Under constructionLast site inspection December 16, 2025 · 11 months ago
68.5%complete

When DLD first inspected the site on Jan 26, 2024, it was 0% complete. After 4 inspections it now stands at 68.5%.

That is about 3% more of the building completed each month on average.

First inspection · 0%Latest · 68.5%
Construction started
April 20, 2024
Completion date registered with DLD
December 30, 2025
Site inspections
4
Units
223
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2938

Latest site photos

December 16, 2025

Progress over time

Progress over time
0%25%50%75%100%2025

Inspection history

  1. December 16, 2025

    5 months after the previous inspection

    +28.1%68.5%
  2. August 1, 2025

    4 months after the previous inspection

    +17.8%40.4%
  3. April 2, 2025

    14 months after the previous inspection

    +22.6%22.6%
  4. January 26, 2024

    First inspection

    0%

Thinking about Gardens 2 by IMAN Developers at Arjan Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2938), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.