Franck Muller Vanguard at Dubai Marina

Construction progress

Franck Muller Vanguard at Dubai Marina construction updates

Dubai Marina · London Gate Real Estate Development L.L.C

Under constructionLast site inspection April 30, 2026 · 6 months ago
48.3%complete

When DLD first inspected the site on Aug 29, 2024, it was 27.7% complete. After 5 inspections it now stands at 48.3%.

That is about 1% more of the building completed each month on average.

First inspection · 27.7%Latest · 48.3%
Construction started
November 1, 2024
Completion date registered with DLD
November 1, 2027
Site inspections
5
Units
771
Escrow bank
Abu Dhabi Islamic Bank
DLD project no.
3202

Latest site photos

April 30, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. April 30, 2026

    3 months after the previous inspection

    +8.3%48.3%
  2. January 20, 2026

    4 months after the previous inspection

    +6.5%40%
  3. October 1, 2025

    6 months after the previous inspection

    +5.8%33.5%
  4. March 20, 2025

    7 months after the previous inspection

    27.7%
  5. August 29, 2024

    First inspection

    27.7%

Thinking about Franck Muller Vanguard at Dubai Marina?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3202), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.