Forest City Tower at Majan, Dubai

Construction progress

Forest City Tower at Majan, Dubai construction updates

Majan · Al Helal Al Zahaby Real Estate Development L.L.C

Under constructionLast site inspection August 13, 2026 · 3 months ago
70.1%complete

When DLD first inspected the site on Oct 24, 2024, it was 0% complete. After 6 inspections it now stands at 70.1%.

That is about 3.2% more of the building completed each month on average.

First inspection · 0%Latest · 70.1%
Construction started
October 10, 2024
Completion date registered with DLD
April 9, 2027
Site inspections
6
Units
253
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
3330

Latest site photos

August 13, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 13, 2026

    3 months after the previous inspection

    +14.1%70.1%
  2. May 8, 2026

    3 months after the previous inspection

    +18.5%56%
  3. February 3, 2026

    3 months after the previous inspection

    +16.6%37.5%
  4. October 24, 2025

    5 months after the previous inspection

    +7.7%20.9%
  5. May 22, 2025

    7 months after the previous inspection

    +13.2%13.2%
  6. October 24, 2024

    First inspection

    0%

Thinking about Forest City Tower at Majan, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3330), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.