Under constructionLast site inspection October 20, 2026 · 18 days ago
11.3%complete

When DLD first inspected the site on Dec 4, 2024, it was 0% complete. After 5 inspections it now stands at 11.3%.

That is about 0.5% more of the building completed each month on average.

First inspection · 0%Latest · 11.3%
Construction started
December 18, 2024
Completion date registered with DLD
January 18, 2028
Site inspections
5
Units
251
Buildings
3
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
3440

Latest site photos

October 20, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 20, 2026

    3 months after the previous inspection

    +4.1%11.3%
  2. July 15, 2026

    3 months after the previous inspection

    +2.4%7.2%
  3. April 3, 2026

    6 months after the previous inspection

    +2.5%4.8%
  4. October 7, 2025

    10 months after the previous inspection

    +2.4%2.4%
  5. December 4, 2024

    First inspection

    0%

Thinking about Flora Isle at Dubai Islands?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3440), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat