Floarea Residence at Arjan

Construction progress

Floarea Residence at Arjan construction updates

Arjan Dubai · Mashriq Elite Real Estate Development L.L.C

CompletedLast site inspection August 14, 2025 · 15 months ago
100%complete

DLD first inspected the site on May 18, 2023 at 1% complete, and recorded it as finished after 6 inspections, the last on Aug 14, 2025.

First inspection · 1%Latest · 100%
Construction started
March 24, 2023
Completion date registered with DLD
April 1, 2025
Site inspections
6
Units
206
Escrow bank
Mashreq Bank Psc
DLD project no.
2651

Latest site photos

August 14, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. August 14, 2025

    6 months after the previous inspection

    +17.8%100%
  2. February 18, 2025

    3 months after the previous inspection

    +11%82.2%
  3. November 29, 2024

    4 months after the previous inspection

    +20.8%71.2%
  4. July 24, 2024

    4 months after the previous inspection

    +20.3%50.4%
  5. March 18, 2024

    10 months after the previous inspection

    +29.1%30.1%
  6. May 18, 2023

    First inspection

    1%

Thinking about Floarea Residence at Arjan?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2651), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.