Fairway Residences at Sports City Dubai

Construction progress

Fairway Residences at Sports City Dubai construction updates

Sports City Dubai · Prescott Real Estate Development L.L.C

Under constructionLast site inspection September 30, 2026 · 37 days ago
50%complete

When DLD first inspected the site on May 15, 2024, it was 0% complete. After 8 inspections it now stands at 50%.

That is about 1.8% more of the building completed each month on average.

First inspection · 0%Latest · 50%
Construction started
June 1, 2024
Site inspections
8
Units
156
Escrow bank
United Bank Limited (Management Office)
DLD project no.
3086

Latest site photos

September 30, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 30, 2026

    3 months after the previous inspection

    +7.4%50%
  2. June 23, 2026

    3 months after the previous inspection

    +9.9%42.7%
  3. March 18, 2026

    3 months after the previous inspection

    +11.6%32.8%
  4. December 18, 2025

    2 months after the previous inspection

    +4.9%21.2%
  5. October 17, 2025

    5 months after the previous inspection

    +8.9%16.3%
  6. May 19, 2025

    4 months after the previous inspection

    +5.9%7.4%
  7. January 28, 2025

    8 months after the previous inspection

    +1.5%1.5%
  8. May 15, 2024

    First inspection

    0%

Thinking about Fairway Residences at Sports City Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3086), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.