Estrella at Majan by Nexus Developer

Construction progress

Estrella at Majan by Nexus Developer construction updates

Majan · Nexus Capital Real Estate Developement L.L.C

Under constructionLast site inspection May 21, 2026 · 6 months ago
45.5%complete

When DLD first inspected the site on Oct 16, 2024, it was 3.9% complete. After 4 inspections it now stands at 45.5%.

That is about 2.2% more of the building completed each month on average.

First inspection · 3.9%Latest · 45.5%
Construction started
July 1, 2024
Completion date registered with DLD
May 31, 2026
Site inspections
4
Units
60
Escrow bank
United Bank Limited (Management Office)
DLD project no.
3284

Latest site photos

May 21, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. May 21, 2026

    3 months after the previous inspection

    +7%45.5%
  2. February 5, 2026

    6 months after the previous inspection

    +23.3%38.5%
  3. August 4, 2025

    10 months after the previous inspection

    +11.3%15.2%
  4. October 16, 2024

    First inspection

    3.9%

Thinking about Estrella at Majan by Nexus Developer?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3284), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.