Construction progress

Esme Beach Residences construction updates

Dubai Islands · Elysian Luxury Real Estate Development L.L.C

Under constructionLast site inspection September 3, 2026 · 2 months ago
14.4%complete

When DLD first inspected the site on Nov 21, 2024, it was 0% complete. After 4 inspections it now stands at 14.4%.

That is about 0.7% more of the building completed each month on average.

First inspection · 0%Latest · 14.4%
Construction started
January 1, 2025
Completion date registered with DLD
April 1, 2027
Site inspections
4
Units
109
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3410

Latest site photos

September 3, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 3, 2026

    5 months after the previous inspection

    +8.4%14.4%
  2. April 14, 2026

    5 months after the previous inspection

    +2.3%6%
  3. October 30, 2025

    11 months after the previous inspection

    +3.7%3.7%
  4. November 21, 2024

    First inspection

    0%

Thinking about Esme Beach Residences?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3410), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.