Enqlave at Al Furjan by Aqasa

Construction progress

Enqlave at Al Furjan by Aqasa construction updates

Al Furjan · Aqasa Homes Developers L.L.C

Under constructionLast site inspection September 22, 2026 · 2 months ago
70.3%complete

When DLD first inspected the site on Mar 29, 2024, it was 0% complete. After 6 inspections it now stands at 70.3%.

That is about 2.4% more of the building completed each month on average.

First inspection · 0%Latest · 70.3%
Construction started
May 28, 2024
Site inspections
6
Units
159
Escrow bank
Mashreq Bank Psc
DLD project no.
2959

Latest site photos

September 22, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 22, 2026

    3 months after the previous inspection

    +12.6%70.3%
  2. June 11, 2026

    5 months after the previous inspection

    +17.5%57.7%
  3. January 22, 2026

    3 months after the previous inspection

    +14.8%40.2%
  4. October 13, 2025

    3 months after the previous inspection

    +9.7%25.4%
  5. July 8, 2025

    15 months after the previous inspection

    +15.7%15.7%
  6. March 29, 2024

    First inspection

    0%

Thinking about Enqlave at Al Furjan by Aqasa?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2959), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.