Construction progress
Dubai Science Park · Empire Real Estate Developments L.L.C
When DLD first inspected the site on Jul 23, 2024, it was 0% complete. After 5 inspections it now stands at 13.3%.
That is about 0.6% more of the building completed each month on average.
July 31, 2026
3 months after the previous inspection
5 months after the previous inspection
5 months after the previous inspection
12 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3181), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.