Emerald Vision Tower at JVT, Dubai

Construction progress

Emerald Vision Tower at JVT, Dubai construction updates

JVT · Vision Avenue Homes (Fzc)

CompletedLast site inspection August 15, 2025 · 15 months ago
100%complete

DLD first inspected the site on Oct 27, 2023 at 42% complete, and recorded it as finished after 3 inspections, the last on Aug 15, 2025.

First inspection · 42%Latest · 100%
Construction started
October 5, 2022
Site inspections
3
Units
141
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
2805

Latest site photos

August 15, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. August 15, 2025

    9 months after the previous inspection

    +8.9%100%
  2. November 13, 2024

    13 months after the previous inspection

    +49.1%91.1%
  3. October 27, 2023

    First inspection

    42%

Thinking about Emerald Vision Tower at JVT, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2805), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat