Elysee Heights at JVC Dubai

Construction progress

Elysee Heights at JVC Dubai construction updates

JVC · Pantheon Elysee Real Estate Development L.L.C

Under constructionLast site inspection June 1, 2026 · 5 months ago
81.3%complete

When DLD first inspected the site on May 22, 2023, it was 0% complete. After 6 inspections it now stands at 81.3%.

That is about 2.2% more of the building completed each month on average.

First inspection · 0%Latest · 81.3%
Construction started
April 15, 2023
Completion date registered with DLD
April 14, 2026
Site inspections
6
Units
193
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2660

Latest site photos

June 1, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. June 1, 2026

    4 months after the previous inspection

    +23.7%81.3%
  2. February 4, 2026

    3 months after the previous inspection

    +10.2%57.6%
  3. October 24, 2025

    6 months after the previous inspection

    +15.4%47.4%
  4. May 6, 2025

    18 months after the previous inspection

    +31.9%31.9%
  5. November 20, 2023

    6 months after the previous inspection

    +0%0%
  6. May 22, 2023

    First inspection

    0%

Thinking about Elysee Heights at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2660), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.