ELTIERA Heights by Ellington

Construction progress

ELTIERA Heights by Ellington construction updates

Jumeirah Bay Island · Ellington Pcfc Developers L.L.C

Under constructionLast site inspection July 20, 2026 · 4 months ago
3%complete

When DLD first inspected the site on Jul 2, 2025, it was 0% complete. After 3 inspections it now stands at 3%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 3%
Construction started
June 19, 2025
Completion date registered with DLD
December 31, 2028
Site inspections
3
Units
357
Escrow bank
National Bank Of Ras Al- Khaimah (P.S.C)
DLD project no.
3852

Latest site photos

July 20, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. July 20, 2026

    4 months after the previous inspection

    +2.7%3%
  2. March 13, 2026

    8 months after the previous inspection

    +0.3%0.3%
  3. July 2, 2025

    First inspection

    0%

Thinking about ELTIERA Heights by Ellington?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3852), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.