Construction progress
Jebel Ali Village · Deyaar Development (P.J.S.C)
When DLD first inspected the site on Feb 16, 2024, it was 0% complete. After 6 inspections it now stands at 20%.
That is about 0.6% more of the building completed each month on average.
September 24, 2026
3 months after the previous inspection
3 months after the previous inspection
4 months after the previous inspection
1 day after the previous inspection
21 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 2965), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.