Construction progress

Electra at JVC by ACube Developers construction updates

JVC · Acube Real Estate Development L L C

Under constructionLast site inspection October 19, 2026 · 19 days ago
9.2%complete

When DLD first inspected the site on Apr 4, 2024, it was 0% complete. After 8 inspections it now stands at 9.2%.

That is about 0.3% more of the building completed each month on average.

First inspection · 0%Latest · 9.2%
Construction started
April 30, 2024
Site inspections
8
Units
281
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
2881

Latest site photos

October 19, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 19, 2026

    3 months after the previous inspection

    +1.4%9.2%
  2. July 6, 2026

    2 months after the previous inspection

    +0.3%7.9%
  3. May 21, 2026

    2 months after the previous inspection

    +0.9%7.6%
  4. March 16, 2026

    8 months after the previous inspection

    +1.1%6.7%
  5. July 17, 2025

    3 months after the previous inspection

    +0.7%5.6%
  6. April 2, 2025

    5 months after the previous inspection

    +4.6%4.9%
  7. November 14, 2024

    7 months after the previous inspection

    +0.3%0.3%
  8. April 4, 2024

    First inspection

    0%

Thinking about Electra at JVC by ACube Developers?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2881), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.