Elbrus Tower at JVT

Construction progress

Elbrus Tower at JVT construction updates

JVT · Tiger Properties

CompletedLast site inspection September 2, 2026 · 2 months ago
100%complete

DLD first inspected the site on May 5, 2023 at 0% complete, and recorded it as finished after 11 inspections, the last on Sep 2, 2026.

First inspection · 0%Latest · 100%
Construction started
June 1, 2023
Completion date registered with DLD
March 31, 2026
Site inspections
11
Units
270
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2637

Latest site photos

September 2, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 2, 2026

    13 days after the previous inspection

    +1.2%100%
  2. August 20, 2026

    10 days after the previous inspection

    +1.2%98.8%
  3. August 10, 2026

    11 days after the previous inspection

    +0.2%97.6%
  4. July 30, 2026

    3 months after the previous inspection

    +3.5%97.3%
  5. April 27, 2026

    4 months after the previous inspection

    +18.8%93.8%
  6. December 30, 2025

    5 months after the previous inspection

    +34.8%75%
  7. July 18, 2025

    5 months after the previous inspection

    +23%40.2%
  8. February 18, 2025

    7 months after the previous inspection

    +15.1%17.2%
  9. July 8, 2024

    0 days after the previous inspection

    2.2%
  10. July 8, 2024

    14 months after the previous inspection

    +2.2%2.2%
  11. May 5, 2023

    First inspection

    0%

Thinking about Elbrus Tower at JVT?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2637), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.