Elaya by Nshama at Town Square Dubai

Construction progress

Elaya by Nshama at Town Square Dubai construction updates

Town Square · Nshama Properties Owned By Nshmi Development One Person Company L.L.C

CompletedLast site inspection October 26, 2026 · 11 days ago
100%complete

DLD first inspected the site on Feb 26, 2024 at 0% complete, and recorded it as finished after 8 inspections, the last on Oct 26, 2026.

First inspection · 0%Latest · 100%
Construction started
September 27, 2024
Site inspections
8
Units
153
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2986

Latest site photos

October 26, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 26, 2026

    6 months after the previous inspection

    +47.9%100%
  2. April 30, 2026

    4 months after the previous inspection

    +10.4%52.1%
  3. January 9, 2026

    0 days after the previous inspection

    41.7%
  4. January 9, 2026

    3 months after the previous inspection

    +15.4%41.7%
  5. October 6, 2025

    8 months after the previous inspection

    +20.1%26.3%
  6. January 24, 2025

    11 months after the previous inspection

    +6.2%6.2%
  7. February 26, 2024

    0 days after the previous inspection

    0%
  8. February 26, 2024

    First inspection

    0%

Thinking about Elaya by Nshama at Town Square Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2986), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.