Elaris Rise at JVT, Dubai

Construction progress

Elaris Rise at JVT, Dubai construction updates

JVT · Object One Real Estate Development L.L.C

Under constructionLast site inspection October 29, 2026 · 8 days ago
3.6%complete

When DLD first inspected the site on Aug 21, 2025, it was 0% complete. After 4 inspections it now stands at 3.6%.

That is about 0.3% more of the building completed each month on average.

First inspection · 0%Latest · 3.6%
Construction started
October 15, 2025
Completion date registered with DLD
September 30, 2028
Site inspections
4
Units
214
Escrow bank
Abu Dhabi Islamic Bank
DLD project no.
4018

Latest site photos

October 29, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 29, 2026

    3 months after the previous inspection

    +2%3.6%
  2. July 30, 2026

    3 months after the previous inspection

    +1.7%1.7%
  3. April 23, 2026

    8 months after the previous inspection

    +0%0%
  4. August 21, 2025

    First inspection

    0%

Thinking about Elaris Rise at JVT, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4018), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat