Divine Residencia at Dubai Studio City

Construction progress

Divine Residencia at Dubai Studio City construction updates

Dubai Studio City · Takmeel Real Estate Development L.L.C

CompletedLast site inspection April 13, 2026 · 7 months ago
100%complete

DLD first inspected the site on Dec 20, 2023 at 0% complete, and recorded it as finished after 6 inspections, the last on Apr 13, 2026.

First inspection · 0%Latest · 100%
Construction started
February 1, 2024
Site inspections
6
Units
69
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2849

Latest site photos

April 13, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. April 13, 2026

    2 months after the previous inspection

    +3.9%100%
  2. January 28, 2026

    4 months after the previous inspection

    +22.7%96.1%
  3. October 10, 2025

    6 months after the previous inspection

    +23.5%73.3%
  4. April 9, 2025

    6 months after the previous inspection

    +32.6%49.9%
  5. October 23, 2024

    10 months after the previous inspection

    +17.2%17.2%
  6. December 20, 2023

    First inspection

    0%

Thinking about Divine Residencia at Dubai Studio City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2849), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.