Divine Living at Arjan Dubai

Construction progress

Divine Living at Arjan Dubai construction updates

Arjan Dubai · Takmeel Real Estate Development L.L.C

CompletedLast site inspection September 22, 2025 · 14 months ago
100%complete

DLD first inspected the site on May 18, 2023 at 10.4% complete, and recorded it as finished after 7 inspections, the last on Sep 22, 2025.

First inspection · 10.4%Latest · 100%
Construction started
November 21, 2022
Completion date registered with DLD
June 24, 2024
Site inspections
7
Units
118
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2613

Latest site photos

September 22, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. September 22, 2025

    9 months after the previous inspection

    +19.2%100%
  2. December 25, 2024

    4 months after the previous inspection

    +12.3%80.8%
  3. August 14, 2024

    3 months after the previous inspection

    +17.9%68.5%
  4. May 14, 2024

    4 months after the previous inspection

    +11.8%50.6%
  5. January 24, 2024

    4 months after the previous inspection

    +14.8%38.8%
  6. September 26, 2023

    4 months after the previous inspection

    +13.7%24%
  7. May 18, 2023

    First inspection

    10.4%

Thinking about Divine Living at Arjan Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2613), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.