Diamondz by Danube at JLT Dubai

Construction progress

Diamondz by Danube at JLT Dubai construction updates

JLT · Danube Properties Development L.L.C

Under constructionLast site inspection October 27, 2026 · 11 days ago
18.5%complete

When DLD first inspected the site on Mar 27, 2024, it was 0% complete. After 9 inspections it now stands at 18.5%.

That is about 0.6% more of the building completed each month on average.

First inspection · 0%Latest · 18.5%
Construction started
September 1, 2024
Site inspections
9
Units
1,225
Escrow bank
Ajman Bank /P.J.S.C
DLD project no.
3017

Latest site photos

October 27, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 27, 2026

    3 months after the previous inspection

    +2.2%18.5%
  2. July 20, 2026

    4 months after the previous inspection

    +4.8%16.3%
  3. April 1, 2026

    3 months after the previous inspection

    +1.9%11.5%
  4. December 22, 2025

    4 months after the previous inspection

    +0.2%9.6%
  5. August 26, 2025

    3 months after the previous inspection

    +2.9%9.5%
  6. June 3, 2025

    5 months after the previous inspection

    +2.4%6.6%
  7. January 9, 2025

    29 days after the previous inspection

    +1%4.2%
  8. December 11, 2024

    9 months after the previous inspection

    +3.2%3.2%
  9. March 27, 2024

    First inspection

    0%

Thinking about Diamondz by Danube at JLT Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3017), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat