Cybele by Wadan at DLRC, Dubailand

Construction progress

Cybele by Wadan at DLRC, Dubailand construction updates

Dubai Land Residence Complex (DLRC) · Wadan Real Estate Development L.L.C

Under constructionLast site inspection July 27, 2026 · 3 months ago
2%complete

When DLD first inspected the site on Nov 13, 2025, it was 0% complete. After 3 inspections it now stands at 2%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 2%
Construction started
December 30, 2025
Completion date registered with DLD
December 30, 2027
Site inspections
3
Units
232
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
4222

Latest site photos

July 27, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. July 27, 2026

    3 months after the previous inspection

    +1.9%2%
  2. April 22, 2026

    5 months after the previous inspection

    +0.2%0.2%
  3. November 13, 2025

    First inspection

    0%

Thinking about Cybele by Wadan at DLRC, Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4222), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat