Cove Grand at DubaiLand Residence Complex (DLRC)

Construction progress

Cove Grand at DubaiLand Residence Complex (DLRC) construction updates

Dubai Land Residence Complex (DLRC) · Imtiaz Cove Real Estate Development L.L.C

Under constructionLast site inspection October 8, 2026 · 30 days ago
13.4%complete

When DLD first inspected the site on May 19, 2025, it was 0% complete. After 6 inspections it now stands at 13.4%.

That is about 0.8% more of the building completed each month on average.

First inspection · 0%Latest · 13.4%
Construction started
May 30, 2025
Completion date registered with DLD
December 15, 2027
Site inspections
6
Units
538
Escrow bank
Ajman Bank /P.J.S.C
DLD project no.
3774

Latest site photos

October 8, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 8, 2026

    3 months after the previous inspection

    +4.7%13.4%
  2. July 8, 2026

    2 months after the previous inspection

    +2.4%8.7%
  3. April 29, 2026

    3 months after the previous inspection

    +1%6.3%
  4. January 20, 2026

    3 months after the previous inspection

    +3.6%5.2%
  5. October 6, 2025

    5 months after the previous inspection

    +1.7%1.7%
  6. May 19, 2025

    First inspection

    0%

Thinking about Cove Grand at DubaiLand Residence Complex (DLRC)?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3774), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat