Cove Edition 6 by Imtiaz at DLRC

Construction progress

Cove Edition 6 by Imtiaz at DLRC construction updates

Dubai Land Residence Complex (DLRC) · Imtiaz Cove Real Estate Development L.L.C

Under constructionLast site inspection October 13, 2026 · 25 days ago
25.9%complete

When DLD first inspected the site on Jun 2, 2025, it was 0% complete. After 6 inspections it now stands at 25.9%.

That is about 1.6% more of the building completed each month on average.

First inspection · 0%Latest · 25.9%
Construction started
June 10, 2025
Completion date registered with DLD
September 10, 2027
Site inspections
6
Units
264
Escrow bank
Ajman Bank /P.J.S.C
DLD project no.
3803

Latest site photos

October 13, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 13, 2026

    3 months after the previous inspection

    +5.8%25.9%
  2. July 13, 2026

    3 months after the previous inspection

    +13.8%20.1%
  3. April 8, 2026

    2 months after the previous inspection

    +2.1%6.3%
  4. February 5, 2026

    4 months after the previous inspection

    +3.2%4.2%
  5. October 20, 2025

    5 months after the previous inspection

    +1.1%1.1%
  6. June 2, 2025

    First inspection

    0%

Thinking about Cove Edition 6 by Imtiaz at DLRC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3803), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.