Cove Edition 2 by Imtiaz

Construction progress

Cove Edition 2 by Imtiaz construction updates

Dubailand · Imtiaz Real Estate Investment & Development L.L.C

Under constructionLast site inspection October 20, 2026 · 18 days ago
60.1%complete

When DLD first inspected the site on Sep 9, 2024, it was 0% complete. After 8 inspections it now stands at 60.1%.

That is about 2.4% more of the building completed each month on average.

First inspection · 0%Latest · 60.1%
Construction started
October 15, 2024
Completion date registered with DLD
October 15, 2026
Site inspections
8
Units
260
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3286

Latest site photos

October 20, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 20, 2026

    2 months after the previous inspection

    +10.1%60.1%
  2. August 17, 2026

    2 months after the previous inspection

    +13.6%50%
  3. June 3, 2026

    3 months after the previous inspection

    +12.3%36.4%
  4. February 26, 2026

    5 months after the previous inspection

    +14.1%24.1%
  5. October 8, 2025

    4 months after the previous inspection

    +6.5%10%
  6. June 4, 2025

    4 months after the previous inspection

    +3.5%3.5%
  7. February 4, 2025

    5 months after the previous inspection

    +0%0%
  8. September 9, 2024

    First inspection

    0%

Thinking about Cove Edition 2 by Imtiaz?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3286), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.