Cove Boulevard by Imtiaz at Dubailand

Construction progress

Cove Boulevard by Imtiaz at Dubailand construction updates

Dubailand · Imtiaz Real Estate Investment & Development L.L.C

Under constructionLast site inspection September 30, 2026 · 38 days ago
10.5%complete

When DLD first inspected the site on Apr 10, 2025, it was 0% complete. After 7 inspections it now stands at 10.5%.

That is about 0.6% more of the building completed each month on average.

First inspection · 0%Latest · 10.5%
Construction started
May 25, 2025
Completion date registered with DLD
October 30, 2028
Site inspections
7
Units
436
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3675

Latest site photos

September 30, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. September 30, 2026

    5 months after the previous inspection

    +4.5%10.5%
  2. April 27, 2026

    3 months after the previous inspection

    +1.6%5.9%
  3. January 27, 2026

    3 months after the previous inspection

    +3.2%4.3%
  4. October 24, 2025

    11 days after the previous inspection

    +0.6%1.1%
  5. October 13, 2025

    3 months after the previous inspection

    +0.4%0.6%
  6. June 30, 2025

    3 months after the previous inspection

    +0.1%0.1%
  7. April 10, 2025

    First inspection

    0%

Thinking about Cove Boulevard by Imtiaz at Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3675), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.