Coral Reef by Damac at Dubai Maritime City

Construction progress

Coral Reef by Damac at Dubai Maritime City construction updates

Dubai Maritime City · Damac P S L Investment L.L.C

Under constructionLast site inspection August 10, 2026 · 3 months ago
32.9%complete

When DLD first inspected the site on Jul 20, 2023, it was 0% complete. After 7 inspections it now stands at 32.9%.

That is about 0.9% more of the building completed each month on average.

First inspection · 0%Latest · 32.9%
Construction started
October 18, 2023
Site inspections
7
Units
280
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
2729

Latest site photos

August 10, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 10, 2026

    3 months after the previous inspection

    +5.5%32.9%
  2. April 29, 2026

    5 months after the previous inspection

    +9%27.4%
  3. December 8, 2025

    6 months after the previous inspection

    +5.9%18.4%
  4. June 20, 2025

    5 months after the previous inspection

    +5.1%12.5%
  5. January 22, 2025

    7 months after the previous inspection

    +6.7%7.5%
  6. July 5, 2024

    12 months after the previous inspection

    +0.7%0.7%
  7. July 20, 2023

    First inspection

    0%

Thinking about Coral Reef by Damac at Dubai Maritime City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2729), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.