Coral by Vision at Al Satwa, Dubai

Construction progress

Coral by Vision at Al Satwa, Dubai construction updates

Al Satwa Dubai · Clear Vision Real Estate Development L.L.C

CompletedLast site inspection February 11, 2026 · 9 months ago
100%complete

DLD first inspected the site on Apr 25, 2024 at 0% complete, and recorded it as finished after 6 inspections, the last on Feb 11, 2026.

First inspection · 0%Latest · 100%
Construction started
July 1, 2024
Completion date registered with DLD
December 31, 2025
Site inspections
6
Units
88
Escrow bank
The National Bank Of Fujairah P S C
DLD project no.
3037

Latest site photos

February 11, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. February 11, 2026

    21 days after the previous inspection

    +2%100%
  2. January 21, 2026

    9 months after the previous inspection

    +46.8%98%
  3. April 16, 2025

    5 months after the previous inspection

    +31.1%51.2%
  4. November 5, 2024

    35 days after the previous inspection

    +6.5%20.1%
  5. October 1, 2024

    5 months after the previous inspection

    +13.6%13.6%
  6. April 25, 2024

    First inspection

    0%

Thinking about Coral by Vision at Al Satwa, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3037), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.