Construction progress
Dubailand · Majid Al Futtaim Ghaf Woods L.L.C
When DLD first inspected the site on May 9, 2024, it was 0% complete. After 7 inspections it now stands at 43.8%.
That is about 1.6% more of the building completed each month on average.
August 17, 2026
0 days after the previous inspection
42 days after the previous inspection
3 months after the previous inspection
4 months after the previous inspection
0 days after the previous inspection
19 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3016), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.