Chelsea Residences by Damac

Construction progress

Chelsea Residences by Damac construction updates

Dubai Maritime City · Damac Crest Development L.L.C

Under constructionLast site inspection August 7, 2026 · 3 months ago
5.2%complete

When DLD first inspected the site on Apr 24, 2025, it was 0% complete. After 4 inspections it now stands at 5.2%.

That is about 0.3% more of the building completed each month on average.

First inspection · 0%Latest · 5.2%
Construction started
July 19, 2025
Completion date registered with DLD
December 31, 2029
Site inspections
4
Units
703
Buildings
3
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3719

Latest site photos

August 7, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. August 7, 2026

    4 months after the previous inspection

    +4.5%5.2%
  2. April 9, 2026

    6 months after the previous inspection

    +0.6%0.7%
  3. October 23, 2025

    6 months after the previous inspection

    +0.1%0.1%
  4. April 24, 2025

    First inspection

    0%

Thinking about Chelsea Residences by Damac?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3719), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.