Chelsea Gardens at Al Satwa

Construction progress

Chelsea Gardens at Al Satwa construction updates

Al Satwa Dubai · Alaia Developments L.L.C

Under constructionLast site inspection September 23, 2026 · last month
10.3%complete

When DLD first inspected the site on Feb 7, 2025, it was 0% complete. After 4 inspections it now stands at 10.3%.

That is about 0.5% more of the building completed each month on average.

First inspection · 0%Latest · 10.3%
Construction started
March 1, 2025
Completion date registered with DLD
February 28, 2027
Site inspections
4
Units
59
Escrow bank
Mashreq Bank Psc
DLD project no.
3553

Latest site photos

September 23, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. September 23, 2026

    4 months after the previous inspection

    +7.1%10.3%
  2. May 12, 2026

    4 months after the previous inspection

    +1.2%3.2%
  3. December 30, 2025

    11 months after the previous inspection

    +2%2%
  4. February 7, 2025

    First inspection

    0%

Thinking about Chelsea Gardens at Al Satwa?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3553), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.