Celeste by Westar at JVC Dubai

Construction progress

Celeste by Westar at JVC Dubai construction updates

JVC · Westar Properties L.L.C

CompletedLast site inspection November 27, 2025 · 11 months ago
100%complete

DLD first inspected the site on Feb 13, 2024 at 0% complete, and recorded it as finished after 4 inspections, the last on Nov 27, 2025.

First inspection · 0%Latest · 100%
Construction started
June 30, 2024
Completion date registered with DLD
December 31, 2025
Site inspections
4
Units
15
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2916

Latest site photos

November 27, 2025

Progress over time

Progress over time
0%25%50%75%100%2025

Inspection history

  1. November 27, 2025

    5 months after the previous inspection

    +18.4%100%
  2. June 13, 2025

    6 months after the previous inspection

    +61.4%81.6%
  3. December 4, 2024

    10 months after the previous inspection

    +20.2%20.2%
  4. February 13, 2024

    First inspection

    0%

Thinking about Celeste by Westar at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2916), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.