Cavendish Square at JVT Dubai

Construction progress

Cavendish Square at JVT Dubai construction updates

JVT · Leos Development L.L.C

Under constructionLast site inspection August 6, 2026 · 3 months ago
4.6%complete

When DLD first inspected the site on Nov 28, 2023, it was 0% complete. After 5 inspections it now stands at 4.6%.

That is about 0.1% more of the building completed each month on average.

First inspection · 0%Latest · 4.6%
Construction started
January 7, 2024
Site inspections
5
Units
141
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
2866

Latest site photos

August 6, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 6, 2026

    2 months after the previous inspection

    +0.3%4.6%
  2. June 4, 2026

    2 months after the previous inspection

    4.4%
  3. April 6, 2026

    8 months after the previous inspection

    +3.1%4.4%
  4. July 29, 2025

    20 months after the previous inspection

    +1.2%1.2%
  5. November 28, 2023

    First inspection

    0%

Thinking about Cavendish Square at JVT Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2866), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.