Cavalli Couture by Damac at Dubai Water Canal

Construction progress

Cavalli Couture by Damac at Dubai Water Canal construction updates

Dubai Water Canal · Damac Business Real Estate Co. L.L.C

Under constructionLast site inspection April 8, 2026 · 7 months ago
19.7%complete

When DLD first inspected the site on Sep 15, 2022, it was 0% complete. After 9 inspections it now stands at 19.7%.

That is about 0.5% more of the building completed each month on average.

First inspection · 0%Latest · 19.7%
Construction started
March 30, 2023
Completion date registered with DLD
May 31, 2025
Site inspections
9
Units
95
Buildings
2
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2459

Latest site photos

April 8, 2026

Progress over time

Progress over time
0%25%50%75%100%2023202420252026

Inspection history

  1. April 8, 2026

    3 months after the previous inspection

    +4.8%19.7%
  2. December 23, 2025

    7 months after the previous inspection

    +4%14.9%
  3. May 30, 2025

    11 months after the previous inspection

    +5%10.9%
  4. July 5, 2024

    37 days after the previous inspection

    +2.2%5.9%
  5. May 29, 2024

    6 months after the previous inspection

    +0.3%3.6%
  6. November 15, 2023

    4 months after the previous inspection

    +1%3.3%
  7. July 4, 2023

    3 months after the previous inspection

    +1.7%2.3%
  8. April 11, 2023

    7 months after the previous inspection

    +0.7%0.7%
  9. September 15, 2022

    First inspection

    0%

Thinking about Cavalli Couture by Damac at Dubai Water Canal?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2459), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.