California Village at Dubailand

Construction progress

California Village at Dubailand construction updates

Dubailand · Gfh Real Estate L.L.C

Under constructionLast site inspection May 8, 2026 · 6 months ago
95.1%complete

When DLD first inspected the site on Jun 13, 2023, it was 1.4% complete. After 8 inspections it now stands at 95.1%.

That is about 2.7% more of the building completed each month on average.

First inspection · 1.4%Latest · 95.1%
Construction started
March 15, 2023
Completion date registered with DLD
July 15, 2025
Site inspections
8
Units
212
Escrow bank
Mashreq Bank Psc
DLD project no.
2694

Latest site photos

May 8, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. May 8, 2026

    5 months after the previous inspection

    +1.9%95.1%
  2. December 8, 2025

    3 months after the previous inspection

    +14.2%93.2%
  3. September 4, 2025

    3 months after the previous inspection

    +8.7%79%
  4. May 21, 2025

    4 months after the previous inspection

    +18.7%70.3%
  5. January 10, 2025

    4 months after the previous inspection

    +11.3%51.5%
  6. September 12, 2024

    6 months after the previous inspection

    +19.9%40.2%
  7. March 14, 2024

    9 months after the previous inspection

    +18.9%20.3%
  8. June 13, 2023

    First inspection

    1.4%

Thinking about California Village at Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2694), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat