Bugatti Residences at Business Bay Dubai

Construction progress

Bugatti Residences at Business Bay Dubai construction updates

Business Bay · Binghatti Developers Fze

Under constructionLast site inspection September 23, 2026 · last month
65.6%complete

When DLD first inspected the site on May 18, 2023, it was 0% complete. After 5 inspections it now stands at 65.6%.

That is about 1.6% more of the building completed each month on average.

First inspection · 0%Latest · 65.6%
Construction started
March 1, 2023
Completion date registered with DLD
December 31, 2025
Site inspections
5
Units
187
Escrow bank
Sharjah Islamic Bank
DLD project no.
2547

Latest site photos

September 23, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 23, 2026

    8 months after the previous inspection

    +13.3%65.6%
  2. January 20, 2026

    0 days after the previous inspection

    52.3%
  3. January 20, 2026

    13 months after the previous inspection

    +32.3%52.3%
  4. December 6, 2024

    19 months after the previous inspection

    +20%20%
  5. May 18, 2023

    First inspection

    0%

Thinking about Bugatti Residences at Business Bay Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2547), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.