Boutique 23 at Culture Village Dubai

Construction progress

Boutique 23 at Culture Village Dubai construction updates

Al Jaddaf · Continental Investments Lmd L.L.C

Under constructionLast site inspection October 13, 2026 · 25 days ago
64.9%complete

When DLD first inspected the site on Dec 7, 2023, it was 0% complete. After 7 inspections it now stands at 64.9%.

That is about 1.9% more of the building completed each month on average.

First inspection · 0%Latest · 64.9%
Construction started
November 24, 2023
Site inspections
7
Units
328
Escrow bank
Sharjah Islamic Bank
DLD project no.
2868

Latest site photos

October 13, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. October 13, 2026

    4 months after the previous inspection

    +15.9%64.9%
  2. June 18, 2026

    4 months after the previous inspection

    +13.9%49%
  3. February 24, 2026

    4 months after the previous inspection

    +9.6%35.1%
  4. October 28, 2025

    4 months after the previous inspection

    +8.6%25.5%
  5. June 25, 2025

    2 months after the previous inspection

    +3.4%16.9%
  6. April 11, 2025

    16 months after the previous inspection

    +13.4%13.4%
  7. December 7, 2023

    First inspection

    0%

Thinking about Boutique 23 at Culture Village Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2868), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.