Construction progress
Downtown Dubai · Emaar Development P.J.S.C.
DLD first inspected the site on Apr 24, 2016 at 1.7% complete, and recorded it as finished after 13 inspections, the last on Sep 17, 2020.
September 17, 2020
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
4 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
4 months after the previous inspection
2 months after the previous inspection
4 months after the previous inspection
3 months after the previous inspection
4 months after the previous inspection
15 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 1561), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.