Blossom 76 at JVC, Dubai

Construction progress

Blossom 76 at JVC, Dubai construction updates

JVC · Tranquil Infra Developers L.L.C

Under constructionLast site inspection August 14, 2026 · 3 months ago
40%complete

When DLD first inspected the site on Jun 19, 2024, it was 0% complete. After 8 inspections it now stands at 40%.

That is about 1.5% more of the building completed each month on average.

First inspection · 0%Latest · 40%
Construction started
August 15, 2024
Completion date registered with DLD
March 26, 2027
Site inspections
8
Units
113
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3113

Latest site photos

August 14, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 14, 2026

    3 months after the previous inspection

    +6%40%
  2. May 12, 2026

    3 months after the previous inspection

    +13%34%
  3. February 5, 2026

    3 months after the previous inspection

    +6.4%21%
  4. November 6, 2025

    2 months after the previous inspection

    +6.2%14.6%
  5. August 26, 2025

    3 months after the previous inspection

    +2.4%8.4%
  6. May 22, 2025

    35 days after the previous inspection

    +1.4%6%
  7. April 17, 2025

    10 months after the previous inspection

    +4.5%4.5%
  8. June 19, 2024

    First inspection

    0%

Thinking about Blossom 76 at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3113), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.