Binghatti Venus at JVC

Construction progress

Binghatti Venus at JVC construction updates

JVC · Binghatti Developers Fze

CompletedLast site inspection October 14, 2024 · 2 years ago
100%complete

DLD first inspected the site on Jul 6, 2023 at 3.7% complete, and recorded it as finished after 3 inspections, the last on Oct 14, 2024.

First inspection · 3.7%Latest · 100%
Construction started
June 1, 2023
Completion date registered with DLD
August 31, 2024
Site inspections
3
Units
191
Escrow bank
Sharjah Islamic Bank
DLD project no.
2671

Latest site photos

October 14, 2024

Progress over time

Progress over time
0%25%50%75%100%2024

Inspection history

  1. October 14, 2024

    10 months after the previous inspection

    +70%100%
  2. December 20, 2023

    5 months after the previous inspection

    +26.3%30%
  3. July 6, 2023

    First inspection

    3.7%

Thinking about Binghatti Venus at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2671), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.