Binghatti SKYRISE at Business Bay Dubai

Construction progress

Binghatti SKYRISE at Business Bay Dubai construction updates

Business Bay · Binghatti Developers Fze

Under constructionLast site inspection October 22, 2026 · 16 days ago
35.9%complete

When DLD first inspected the site on Oct 15, 2024, it was 0.1% complete. After 3 inspections it now stands at 35.9%.

That is about 1.5% more of the building completed each month on average.

First inspection · 0.1%Latest · 35.9%
Construction started
October 15, 2024
Completion date registered with DLD
December 31, 2026
Site inspections
3
Units
3,358
Buildings
4
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3349

Latest site photos

October 22, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 22, 2026

    6 months after the previous inspection

    +13.5%35.9%
  2. April 23, 2026

    18 months after the previous inspection

    +22.3%22.4%
  3. October 15, 2024

    First inspection

    0.1%

Thinking about Binghatti SKYRISE at Business Bay Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3349), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.