Binghatti Skyhall at Business Bay, Dubai

Construction progress

Binghatti Skyhall at Business Bay, Dubai construction updates

Business Bay · Binghatti Developers Fze

Under constructionLast site inspection April 30, 2026 · 6 months ago
31.1%complete

When DLD first inspected the site on Jan 16, 2025, it was 0% complete. After 2 inspections it now stands at 31.1%.

That is about 2% more of the building completed each month on average.

First inspection · 0%Latest · 31.1%
Construction started
February 1, 2025
Completion date registered with DLD
August 31, 2026
Site inspections
2
Units
728
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3504

Latest site photos

April 30, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. April 30, 2026

    15 months after the previous inspection

    +31.1%31.1%
  2. January 16, 2025

    First inspection

    0%

Thinking about Binghatti Skyhall at Business Bay, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3504), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat