Binghatti Orchid at JVC

Construction progress

Binghatti Orchid at JVC construction updates

JVC · Binghatti Developers Fze

CompletedLast site inspection December 19, 2024 · 2 years ago
100%complete

DLD first inspected the site on Jul 28, 2023 at 0% complete, and recorded it as finished after 3 inspections, the last on Dec 19, 2024.

First inspection · 0%Latest · 100%
Construction started
August 1, 2023
Site inspections
3
Units
314
Escrow bank
Sharjah Islamic Bank
DLD project no.
2672

Latest site photos

December 19, 2024

Progress over time

Progress over time
0%25%50%75%100%2024

Inspection history

  1. December 19, 2024

    7 months after the previous inspection

    +35.8%100%
  2. May 27, 2024

    10 months after the previous inspection

    +64.2%64.2%
  3. July 28, 2023

    First inspection

    0%

Thinking about Binghatti Orchid at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2672), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.