Construction progress
JVC · Binghatti Developers Fze
DLD first inspected the site on Mar 21, 2023 at 0% complete, and recorded it as finished after 3 inspections, the last on Dec 13, 2024.
December 13, 2024
13 months after the previous inspection
8 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 2610), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.