Binghatti Onyx at JVC

Construction progress

Binghatti Onyx at JVC construction updates

JVC · Binghatti Developers Fze

CompletedLast site inspection December 13, 2024 · 2 years ago
100%complete

DLD first inspected the site on Mar 21, 2023 at 0% complete, and recorded it as finished after 3 inspections, the last on Dec 13, 2024.

First inspection · 0%Latest · 100%
Construction started
March 23, 2023
Completion date registered with DLD
October 1, 2024
Site inspections
3
Units
507
Escrow bank
Sharjah Islamic Bank
DLD project no.
2610

Latest site photos

December 13, 2024

Progress over time

Progress over time
0%25%50%75%100%2024

Inspection history

  1. December 13, 2024

    13 months after the previous inspection

    +69%100%
  2. November 16, 2023

    8 months after the previous inspection

    +31%31%
  3. March 21, 2023

    First inspection

    0%

Thinking about Binghatti Onyx at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2610), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.